C.A.C.I.A manufactures gearboxes and engine components. In 2007, the company’s business expanded by around 12%.

Situation  

C.A.C.I.A. SA is located in the village of Cacia, on the northern edge of Aveiro. It is in Portugal's third-largest industrial centre. The plant is located on major motorways, enabling fast transportation to the rest of Europe.
  
The plant covers an area of 34 ha, of which 7 consists of buildings.

The site’s design is highly operational, guaranteeing an effective, efficient flow of people, products and equipment.

 

Highlights 

João Tavares, Responsable Environnement :  

 

"2009 was a difficult year owing to the activity downturn, which led us to step up vigilance on our environmental aspects. Management during production stoppage days was important for the plant in terms of controlling its environmental performance."

Significant investments were made to improve the working conditions of operators, including the installation of an air extraction and treatment system, which resulted in a considerable improvement in air quality inside the plant while ensuring the best atmospheric emission conditions.

Key environmental data 

 

2009

Change

since 2008

Change since 2004

Water consumption (thousands of m3)

72.2

5%

-37%

Liquid discharge

 

 

Suspended solids (kg/j)

5.1 

38%

79% 

OM (kg/j)

10

24%

20%

Toxic metals (kg/j)

0.0

-90%

-96%

Atmospheric emissions

 

 

Direct and indirect greenhouse gas emissions (teq CO2)

14,528

*

*

NOx emissions (t)

0.6

-28%

-51%

SO2 emissions (t)

0.0

-42%

-53%

Hazardous waste (t)

953

-30%

*

Energy (MWh LHV)

40,680

-6%

-20%

 

(*): Change in scope / Calculation of atmospheric discharges since 2004

 

Comments :

 

  • Water consumption: water consumption rose owing to an increase in the green space surface area and the corresponding watering needs.
  • Liquid effluents: the increase is linked to the discharge threshold imposed by the town hall.
  • Energy: control of consumption during non-worked days. Application of Group actions on energy savings.
  • Electricity consumption outside production hours in 2009: 9.2% higher than Renault’s internal target.

 

For further details, see registration documents:

 

 

 

Key facts 

  • Address
    CACIA SA APARTADO 10 Cacia 3801-653 Aveiro
  • Activity
    Powertrain/Spare Parts
  • Certifications
    ISO 14001 earned in 2000 and renewed in 2003 and 2007